Preposed procedure for software startup sequence for multi-batteries.
Start comms with each/all batteries.
Wait for all batteries to enter 'safe to operate' mode
-if after 60 seconds a battery is not 'safe to operate', reboot it's LBC.
-restart 60 seconds delay
-if after 60 seconds a battery is still not 'safe to operate', open it's safety contactor
-send out appropriate alarm information
Allow Inverter to request closing of main contactors.
If there are batteries available and inverter requests closing:
-check voltages of batteries are within tolerance (of each other)
-if acceptable, close contactors
Monitor current flow to operational batteries to confirm closing of contactors.