Updating the OSeMOSYS GNU repository
|
Hi Hauke, The following suggestions are (just) to stimulate a discussion around this parameter addition.
|
|
Hi Vignesh, thanks for your comments and considerations!
|
…. The AnnualPeakHour is reverse calculated and corresponds to the demand per hour in the time slice with the highest per hour demand.
|
I have now implemented the new RM in the UTOPIA test model. |
|
Perhaps you could have a look @vignesh1987 ? |
|
@vignesh1987 - would you be able to review this pull request? |
|
|
@NMoksnes and I have been going through this PR. NB:This PR should just be merged if #85 is addressed. If #85 is not addressed the proposed change here would need to be adjusted to be able to consider ReserveMargins in different regions. |
I don't think #85 is going to be resolved soon. Can you develop the same functionality without relying on region functionality, otherwise this PR will just sit here gathering dust! |
|
I will think about how to do it. And try to implement it next week. |
|
Just a quick note that by using the user defined constraints functionality you can set up reserve margin constraints a bit more flexibly than with a fixed model implementation. |
The changes to OSeMOSYS proposed here change the way how the
ReserveMarginis determined.It introduces the new parameter
AnnualPeakHourdependent onr in REGION, y in YEAR, which takes the electricity demand of the hour with the highest electricity demand of the year.Using this parameter the calculation of the
ReserveMarginhas been adopted.The aim of this changes is to have a
ReserveMarginthat is closer to the ones observed in real power systems. The current formulation of theReserveMarginrelates theReserveMarginto the time slice with the highest demand. However, time slices do not necessarily represent one hour. Therefore, theReserveMarginis potentially not accurate.This PR addresses #48